The new kinder will help respond to unmet demand for three and four-year-old kindergarten places in the region by providing a 99-place kinder.

In partnership with the Victorian Government, the City is committed to meeting the demand for kindergarten places in Greater Bendigo.

The new building will be designed using environmentally sustainable building standards and will be fully accessible. It will feature three kinder rooms, two allied health rooms which could be used by maternal and child health and other health services, staff facilities, outdoor play area, kitchen facilities and bathroom amenities.

Plans for the new kindergarten are currently being finalised and construction is planned to start in 2024 for completion in 2025. A service provider to operate the new kinder is expected to be appointed in 2024.

Construction of the kindergarten is stage one of a two-stage project to establish a community hub complex bordered by High, Torrens and Cathcart Streets, Marong. The new kinder will be constructed on the site of the current tennis courts.

Stage two of the project, which is currently unfunded and may take several years to deliver, plans to provide flexible multi-purpose buildings and spaces.

Timeline

Project commencement
Community reference group established
Draft plan on exhibition - November 9 to December 2, 2022
Funding secured for Stage 1
Tender released
Franklin and Walsh Builders have been awarded the tender to build the new Marong Kindergarten. Work will commence in the coming week.
Official sod turning
Construction commenced
All under-slab services, foundation works and entire building slab completed
The name 'Marrungi Wayaparra Community Hub' (translates to 'Meet in Marong' in Djaara Language) has been registered with Geographic Names Victoria and has been gazetted
Framing is up and the roof trusses are on
The roof is being installed